Order of the President of the General Court of 2 December 2011 – Carbunión v Council
(Case T-176/11 R)
Application for interim measures – State aid – Decision on aid intended to facilitate the closure of uncompetitive coal mines – Application for suspension of operation of a measure – Lack of standing to bring proceedings – Lack of concordance with the main action – Non-severability – Inadmissibility – Balance of interests
1. Applications for interim measures – Suspension of operation of a measure – Interim measures – Conditions for granting – Prima facie case – Urgency – Serious and irreparable damage – Cumulative nature – Balancing of all the interests involved – Order of examination and method of verification – Discretion of the court hearing the application for interim relief (Arts 278 TFEU and 279 TFEU; Rules of Procedure of the General Court, Art. 104(2)) (see paras 12-14)
2. Applications for interim measures – Suspension of operation of a measure – Conditions for admissibility – Interest of the applicant in obtaining the suspension sought – Application for partial suspension of the operation of Decision 2010/787 on State aid to facilitate the closure of uncompetitive coal mines – Suspension not capable of changing the applicant’s position – No interest in bringing an action (Art. 278 TFEU) (see paras 17-21)
3. Applications for interim measures – Suspension of operation of a measure – Conditions for admissibility – Application seeking measures outside the context of the dispute in the main proceedings – Inadmissibility (Art. 278 TFEU) (see paras 22-24)
4. Applications for interim measures – Suspension of operation of a measure – Conditions for admissibility – Application for partial suspension of operation of a decision – Decision 2010/787 on State aid to facilitate the closure of uncompetitive coal mines – Suspension involving a modification of the substance of the decision – Inadmissibility (Art. 278 TFEU) (see paras 26-34)
5. Applications for interim measures – Suspension of operation of a measure – Conditions for granting – Balancing of all the interests involved – Concept – Preponderance of the public interest over private interests (Art. 278 TFEU) (see paras 36-39, 41-43)
Re:
APPLICATION for partial suspension of operation of Council Decision 2010/787/EU of 10 December 2010 on State aid to facilitate the closure of uncompetitive coal mines (OJ 2010 L 336, p. 24) and, in the alternative, application for full suspension of operation of that decision.
Operative part
1.
The application for interim measures is dismissed.
2.
Costs are reserved.
Similar documents
- Order of the Court (Fifth Chamber) of 11 December 2014. — Federación Nacional de Empresarios de Minas de Carbón (Carbunión) v Council of the European Union. EU judgments · 11 December 2014
- Order of the President of the General Court of 17 February 2010. — Comunidad Autónoma de Galicia v European Commission. EU judgments · 17 February 2010
- Judgment of the General Court (Second Chamber), 3 December 2014. — Castelnou Energía, SL v European Commission. EU judgments · 3 December 2014
- 2002/826/ECSC: Commission decision of 2 July 2002 on financial measures by Spain in respect of the coal industry in 2001 and in the period 1 January 2002 to 23 July 2002 (Text with EEA relevance.) (notified under document number C(2002) 2438) EU legislation · 2 July 2002
- Opinion of Advocate General Tanchev delivered on 1 June 2017. — SolarWorld AG v Council of the European Union. EU judgments · 1 June 2017
- Commission Decision of 11 December 2001 on the granting by Spain of aid to the coal industry in 2001 (Text with EEA relevance) (notified under document number C(2001) 3975) EU legislation · 11 December 2001